PHASE 2 SET TO BEGIN

The contract for Phase 2 was awarded to Vacri Construction from Binghamton, NY. The bid came in on budget and the project is still on schedule to start Monday, July 29, 2013, and to be completed by November 27, 2013. The focus of Phase 2 is replacing the 100 year old water main as well as sewer upgrades. Most of the work will happen within the construction fence, with some work happening outside from time to time. We will keep the community informed when work happens outside the construction fence and how pedestrian access will be rerouted.