WEEK OF 3/24 – 3/28

Four of the seven telecom vaults have been installed. Starting the week of 3/24 one crew will be installing the last three telecom vaults. A second crew will be installing the duct work to connect to the vaults.

On Monday installation of a telecom vault will occur in Bank Alley outside the construction fence near Tompkins Trust Company. The west sidewalk of Bank Alley will be closed to through traffic on Monday. The entrance to Tompkins Trust can only be accessed from Seneca and Tioga. The work on the State Street duct bank will be inside the construction fence.

Please be aware that partial sidewalk and pedestrian crossing closings will happen from time to time during the construction phase. There will be signage letting pedestrians know the best route to take. We apologize for any inconvenience and we thank you for your patience.