WEEK OF 4/7 – 4/11

Most of the work will be focused on the west end this week. Monday, a new sanitary lateral will be installed at 111 E State St. On Wednesday, a new sanitary lateral will be installed at 110 E State Street. This work will extend outside the construction fence with the sidewalk being closed for most of each day. Temporary orange fencing will be used mark the boundary of the work area as well as to protect pedestrians from the work area.

Tuesday through Friday, Vacri will be working on the storm manhole on the east side of the Cayuga & State St intersection. NYSEG will also be working in that area throughout the week. The north-south crosswalk east of the intersection will be closed during the day as well as the sidewalk on the west end of the Commons.

storm manhole on Cayuga

Another crew will continue to install telecom conduit throughout the rest of the work area.

Please be aware that partial sidewalk and pedestrian crossing closings will happen from time to time during the construction phase. We apologize for any inconvenience and we thank you for your patience.