May 19th – E Seneca & N Tioga St Work

CONSTRUCTION UPDATE
For additional information contact: Commons Project Office
(607) 216-8873

FOR IMMEDIATE RELEASE
Date: May 16, 2014

PROJECT NAME: Commons Repair and Upgrade Project /Seneca Street Work Zone

PROJECT LOCATION: 100/ 200 Block of E Seneca Street

PROJECT START DATE: May 19, 2014

PROJECT DESCRIPTION AND GOAL:
A work zone will be created at the end of the Commons where E. Seneca and N.Tioga Street intersect to connect the new telecom service to the telecom manhole in the parking lane of 100 and 200 E Seneca Street.

LOCAL IMPACTS:
Sections of the 100 and 200 blocks of East Seneca Street will be reduced to one parking lane and one travel lane effective 7AM – 6PM for three days. Travel lanes will be open during non-work hours.

RECOMMENDED DETOURS: No detours are being put in place; however, motorists should expect delays and should seek alternative routes if possible

SCHEDULED COMPLETION DATE:
The work is expected to be complete by the end of the work day on May 21, 2014

-End-