WEEK OF JUNE 16 -20

NSYEG gas will continue to install the gas main on the south side on the 200 block of E State St.

Power and Construction Group will continue to install the new electrical conduit. One crew will be on the south 100 block of E State St near the Race Office Equip building. The east-west sidewalk will be closed in front of the Race Office building on Monday.

Another crew will be working in the west sidewalk of Bank Alley just north of Tompkins Trust Company entrance and will move north toward Seneca St. The sidewalk will be closed to pedestrians in the work area with access to access to Tompkins Trust Company from the south (the Commons) and from the side entrance through the back parking lot off of Seneca Street. And access to Tioga Place, TC3 and M&T Bank will be from Seneca Street.

Vacri will be working in Bank Alley beginning to install footers for the new Bernie Milton Pavilion.