WORK ON 100/200 BLOCK OF E SENECA ST

PROJECT NAME: Commons Repair and Upgrade Project /Seneca Street Work Zone

PROJECT LOCATION: 100/ 200 Block of E Seneca Street

 PROJECT START DATE:  July 13, 2015

PROJECT DESCRIPTION AND GOAL:

A work zone will be created at the end of the Commons where E. Seneca and N.Tioga Street intersect to create a bumpout which extends approximately 8’further into the intersection from the previous curb line and is intended as a pedestrian safety measure.

LOCAL IMPACTS:

Sections of the 100 and 200 blocks of East Seneca Street will be reduced to one parking lane and one travel lane effective 7AM – 6PM for three to five days.  Travel lanes will be open during non-work hours.

RECOMMENDED DETOURS: No detours are being put in place; however, motorists should expect delays and should seek alternative routes if possible

SCHEDULED COMPLETION DATE:

The work is expected to be complete by the end of the work day on July 17, 2015